Thursday 18 June 2015

Wike to support Amaechi's leftover projects

Wike to support Amaechi's leftover projects
The Governor of Rivers State, Nyesom Ezenwo Wike, has expressed satisfaction with the level of work done on the Woji-Akpajo Bridge.

The Governor made his feelings known while inspecting the project.



“The contractor is doing well. It doesn’t matter which administration awarded the contract; it’s a major project that would ease off traffic on Aba road and the slaughter to Woji Road so it’s an Important Road and we commend the contractor for not demobilizing from site despite the fact that he has not been paid for the past one year. I am very happy with what has been done”, Governor Wike said.

Governor Wike explained that the project is key to his administration and promised to complete it within a space of time.


Earlier, the contractor handling the project, Mr. Ellias of Raphael Nigeria Limited who lamented the company has not been paid for over a year, disclosed that the company has received only 68% of funds for the project that is more than 70% completed.

The project was awarded for the sum of N11,055,891,675, and the amount paid so far is N7,035,511,282.34 . 

The Governor also inspected the Port Harcourt Shopping Mall started by Sir Celestine Omehia to ascertain the level of work done and expressed readiness to complete the abandoned mall within a space of three months.